Control Systems 2014

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • 1/10/2014

  • 6 hours

  • Parkland Shop

  • Nolan P.


Work Completed

Created entire drive train electric circuit setup. Made a spreadsheet for parts we need to do the drive train wiring so we can buy the parts we need or get the ones together we have. Planned on making a second drive chassis for testing after bag day. Started epic install process for Labview on new 2014 driver station laptop. Letting it run until tomorrow.

Challenges

none

Work for Next Meeting

Finish final spreadsheet and hopefully order the needed parts. Finish getting Labview installed on laptop, plust FRC updates. Start copying code for new bot.

On Schedule?

We are doing great, and probably have more done than the other subteams.