Work Completed

We mounted horizontal bars in between the vertical support posts on the robot and CADed the whole robot ex. At the time of note submission the plate on the CAD was on the wrong side of the drivetrain frame but Jay is fixing that as I type these notes. We also cleaned our station :D

Challenges

parts no come here :(

Work for Next Meeting

If parts arrive we have a list of things to do here: https://docs.google.com/document/d/1a7wlCdae9-tKLuODP_2vL3eq4uIbfZ_0W3KxWKPGIJI/edit If parts dont arrive, keep improvising things to do on CAD or whatever.

On Schedule?

Since we know what we are going to do when parts arrive we should be able to finish our kicker assembly on the robot relatively quickly so we should be fine with accordance to the schedule given that parts are arriving later than expected when the schedule was created.