Edit

Note Viewer


Shooter 2014

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • 2/14/2014

  • 3 hours

  • Parkland Shop

  • RJ M.


Work Completed

We transferred the shooter tower to the new drive train and added horizontal supports. We secured the gearbox frames on that tower with special pieces that help secure the frame so vibrations don't knock the bolts loose. We put the gearboxes on and found the hex pieces that secure the shooter on the axle. We put snap rings on the gear box axle to secure them. The gearbox is 100% done. We are widening the tower base because it was too narrow, and we are currently putting the tower back on as I type these notes.

Work for Next Meeting

put on the rails

On Schedule?

We are almost done with the shooter - the gearbox is finished we just have to add rails and hook it up with electrical.