Work Completed

Put electrical boards and Talons on our shooter apparatus. Assembled our shooter. Put it on the new chassis, complete with rails. A few T-Nuts on the chassis didn't really work with screws, so we just left them out. There are other ones solid, and it's very stable, so it shouldn't be a problem.

Challenges

we have no idea if this will work

Work for Next Meeting

If other subteams are all done, test test test hook up to electrical

On Schedule?

I guess we're okay, new schedule we're a day behind, but I think we'll be good. Especially if we're leaving the shooter off, then we'll definitely be okay. But even if we're not, it should be fine.