Shooter 2016

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • 2/11/2016

  • 3 hours

  • Shapland Shop

  • Joaqui'n M.


Notes

The mobile version wouldn't let me remove Kate and Jazmin from attendance.

They weren't here 

Work Completed

The shooter was tested again to see how badly it shot. 

The shooter was taken off the robot and tested without the bottom rails. We found that it didn't have enough flywheel weight. 

The shooter was disassembled and Lyle went to grind the shooting rails down to decrease the "choke point."

The rest of the shooter was taken apart to add more flywheel plates. 

The feeder was continued to be assembled for basic tests to see if it runs properly 

Challenges

The shooter sucks right now. It gets stuck at the choke point and the shots are very bad. 

The smaller feeder wheels aren't in yet so we can't assemble and test the full real feeder yet. 

Work for Next Meeting

Continue work on the shooter (grinding plates and adding flywheels). 

Test newly grinder shooter. 

If feeder wheels are in, assemble feeder. If not, perform basic feeder tests on jank feeder. 

On Schedule?

Yes?