Work Completed
Fixed 4096 wifi network. Router's WiFi was turned off for some reason.
Moved carpet down and cleared it for field practice.
Fixed loose electrical connection on Nona.
Organized shelves some more.
Assembled Exchange and (most of) platform field elements. Carpet now needs vacuuming.
Worked on Polly shooter code some more.
Rerouted and fixed some of the stubborn Aquifer lights.
Talked to Laura about her Aquifer ideas for recharge.
More Poly2 strippage.
Challenges
Had some random disconnects from Nona, but pretty sure it was the loose connection.
Work for Next Meeting
Finish set up half-field in basement, so we can:
Start drive team practice this weekend
Write autonomous paths for testing with Polly
Finish updating Poly shooter code
Attempt to align robot with vision target with Limelight (PID).
Continue stripping Poly2 of all useful parts
Continue organizing basement.
Order hardware for the third battery.
Decide on names for one more 2018 battery.
On Schedule?