Work Completed

The rest of the plates for the gearbox and the side extrusion was weight holed. Holes for a plate for the encoder were also added. 

Challenges

There was an issue with mirroring the drivetrain which Chris said he would take care of as it is a simple fix.

Work for Next Meeting

Next meeting we should finalize the drivetrain and start machining parts. 

On Schedule?

Yes we are on schedule to get the drivetrain started.