CAD & Integration 2019

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • Dina H.

  • Jonathan L.

  • Lawrence Z.

  • 1/21/2019

  • 3 hours

  • Aquiferland

  • Lawrence Z.


Work Completed

At the beginning of shop opening, we helped assemble the drivetrain.

Climber CAD -- we mated the L bracket to the motor in the back stilt subassembly and mated pulleys into proper locations.  We also supressed appropriated parts in the front stilt subassembly.

Challenges

Some work from earlier today didn't save, so we had to redo it tonight.  In addition, we had difficulty concentric mating the sprocket to the shaft, and getting the dimensions of the L-bracket holes to match the gearbox's holes (we were off multiple times, and it's actually a rectangle, not a square :O by 0.05 in.).

Work for Next Meeting

Next meeting we should continue working on the climber and figure out how the design for the back of the climber will work.  We also still have bugs with the axle mating and the wheels, but besides that climber CAD is nearly complete.

On Schedule?

Yes, we will be able to fix the mating problems and complete the climber by tomorrow.