CAD & Integration 2019

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • Dina H.

  • Jonathan L.

  • 1/30/2019

  • 3 hours

  • Aquiferland

  • Dina H.


Work Completed

All gussets for both the front and back climber were completed. The gussets for the cargo arm were also CADed. These gussets were added onto the full robot assembly.

Challenges

We had trouble getting the dimensions right for the holes, but other than that we encountered no issues. However, conflicting edits on the main assembly meant that we had to overwrite them, losing some of our work in the process.

Work for Next Meeting

We should get CAM for the climber done by tomorrow and work on the hatch mechanism.

On Schedule?

We were not able to get the CAM done, but we are almost done with the cargo CAD.