CAD & Integration 2019

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • Dina H.

  • Jonathan L.

  • 2/5/2019

  • 3 hours

  • Aquiferland

  • Dina H.


Work Completed

We took a look at the final robot assembly to make sure everything looked good. We helped with routing the climber stilt. We also organized parts needed for the climber hub into different bags so that when the parts were routed, assembly would go much smoother. These organized bags are located in the io tote. Chris is finializing the hatch mechanism.

 

Challenges

None

Work for Next Meeting

Look over the hatch mechanism that Chris finished and help with routing and assembly of subsystems.

On Schedule?

Yes, after Chris finalizes hatch tonight, the robot CAD will be completed.