Ella G, Elan, Jeana, James, Kevin, Zafar, Gabe?, Lucas P.
Work Completed
Training on the horizontal saw (Zach): Ella, Jeana?, Lucas
continue on Saba-Z, the ball screw bracket is not going to be replaced until Boiler Bot, it holds fine (James, Chris), replaced guide stopper? on hatch mechanism
driving practice with Saba Z: Lucas, James
Octa drivetrain: continue with wiring : Lucas, Chris
Frisbee ready for UNI Gala demo, in the garage, batteries, driving station
Challenges
We could not find stuff. No snack, last week was awesome.
Work for Next Meeting
Route turret parts
power tool training
self-directed training
Build 4 FLL field setup kits - The printed instructions are in a fedex box on the FLL table (which I cleaned off). One kit is on the table and the other 3 are on what used to be the Invader Bots FLL pallet. See Bob for details.
Rebuild the FLL tables for the qualifier and championship. See Bob for details.
Atla-Z 1) attach elevator to the chain if we have the small bolts (ordered)
Saba-Z 1) check and/or fix ground connection to the Power distribution panel
Octa drivetrain 1) fix Wire ferrule connectors (ordered? we need Wire ferrules yellow 10mm, we have 8mm, too short) on Rio if we have them (we probably don't), 2) attach two front wheels, 3) wiring and attach main switch