Work Completed

  • Octa DT encoder mounted
  • Octa wiring finished, minus one encoder cable. Need to order/find connector parts for it
  • Saba climber vs. hab switch broke during climb test. Replaced and ready to test. Need to order a couple more Vex bumper-style limit switches

Done last meeting:

  • Rewrite driver controls sheets
  • Replace hatch panel bracket

Chris and James looked over James' swerve module and discussed what needs to be changed before machining one

Challenges

  • Replacing switch, until we moved Saba to workbenches
  • Shop is a mess

Work for Next Meeting

  • Route turret parts
  • power tool training
  • self-directed training
  • CNC training remaining Tuesdays in November. 
  • Finish 1 more FLL field setup kits - The printed instructions are in a fedex box on the FLL table (which I cleaned off).  See Bob for details.
  • Rebuild the FLL tables for the qualifier and championship. See Bob for details.
  • Atla-Z
    • 1) route and replace chain mount on elevator  
    • 2) attach elevator to the chain if we have the small bolts (ordered)
  • Saba-Z FIX for Boiler Bot (11/16)
    • 1) check and/or fix ground connection to the Power distribution panel (wiring - bare wires right now, wait for yellow ferrules or switch to solid wire)
  • Octa drivetrain
    • Wire second DT encoder
  • Driving practice