Climber 2020

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • Lukas G.

  • Marlow T.

  • 1/18/2020

  • 3 hours

  • Aquiferland

  • Marlow T.

Guests

Cadi was also here


Work Completed

Attached strings to moving part of elevator on either side of the mechanism. Used shaft collars to secure the strings to the central shaft. Removed a link of the chain to tighten it. We tested the prototype and it worked but got stuck about 80% of the way up.

Challenges

The elevator got stuck at some points while testing it. The string was slipping before we attached it with shaft collars.

Work for Next Meeting

1 Find out why it was getting stuck at some points when testing. Otherwise it's basically finished.

2. start on new telescoping climber + cad

 

On Schedule?

a bit behind schedule, was supposed to finish this prototype on friday but that's ok