CAD & Integration 2020

Attendance

Note Info

Students
Mentors
Date & Time
Location & Author
  • Dina H.

  • Jonathan L.

  • 1/18/2020

  • 4 hours

  • Aquiferland

  • Dina H.


Work Completed

- added weight holes to the front gearbox plate

- added holes for the flathead screws that hold the two plates together 

- added axles, bearings, spacers, and wheels to the other side of the drivetrain frame

- Assembled the gearbox into the drivetrain assembly & mirrored it across to the other side assembly

Challenges

- had some trouble with the geometry while creating the weightholes

- had some trouble with mirroring causing some bearings to be out of place

Work for Next Meeting

- Make a "crayola CAD" model of the robot with each subsystem as a blocky object just to see how everything will fit on the robot

- Finish adding drivetrain parts to the BOM

- Start CAM

- Start CAD on other subsystems

 

On Schedule?

On schedule to have all parts ordered and CAM done next meeting