Work Completed

- created the main robot assembly, added in the supports and turret

- adjusted the supports to have a cross bar at the top, and extrusions extending down

- started the climber gearbox: ratio 6:60 & 20:68 with two 775pros, finished the plates and almost completed assembly. 

Challenges

- had to figure out how to mount the gearbox on the support extrusions

Work for Next Meeting

- Continue CAM on other extrusions

- finish climber and shooter CAD

- finish lexan plate CAD for the intake + indexer

- FINISH ALL CAD ASAP

 

On Schedule?